[ 2 Feb 2010 ]
The small auditorium is already finished and the large one is progressing at a good pace. By summer, the structure will have been completed.

Area 1 (Auditoriums): The small auditorium is finished and in the other the concrete and the terraces are being finished. The service area has also been concreted and the placing of stonework on the north façade has started. Likewise, part of the metalwork has already been placed on the south façade.

 

Area 2 (Exhibition Rooms): The flooring of the ground floor is being carried out, the metal beams have been installed as well as one corridor which borders the exhibition room, in addition to the structure of the ‘between floor’ areas which make up the viewing platforms of the exhibition rooms.

 

Area 3 (Hotel): The concrete structure has been carried out up to the seventh floor. The metal structures have also been concluded on storeys 1 and 2 in stage 2. This stage has also seen the wrought-iron work completed on the 1st floor.